The City's policies are very critical, even one of the decisive reasons for whether or not you should undertake a renovation. If the City is too tough, you must be cautious. But most cities encourage improving residential properties because it raises the city's image, within certain limits, of course. For example, some areas in the Bay Area must adhere to a specific architectural style. Some cities require a large setback, which restricts the planning.
There are a few things to pay attention to in advance:
-
Setback: This is critical; you must ensure there is enough setback. However, for lenient cities, before renovating, it's best to consider whether to maximize the expansion area as much as possible, as this is the most value-adding investment.
-
Neighbors: If the setback limit is significant, you can consider adding a second floor. Still, if there aren't many 2-story buildings around, the City might not allow it. Be sure to understand this before starting the design.
-
Utility Entrance Locations (Water/Electric): Most renovations require re-introducing electricity. Knowing the location in advance allows for appropriate design. For example, if the electrical panel location is close to the PGE's underground electrical entrance, you can save a lot of cost.
-
Construction Time: This varies by area. For example, some areas do not allow construction on Saturdays, which will not only extend the duration but also increase the communication cost. After all, most people work during the week and don't have time to visit the construction site.
-
Valuation Logic: Clarify what extent of exterior wall movement counts as new construction.
During the renovation process, there are many hidden City compliance items, such as:
-
Fire Safety: Most houses needing renovation do not meet the code, and fire safety (sprinklers) will definitely need to be added. To add fire safety, you will naturally need to update the electrical meter and water supply system. The two combined can exceed $20K.
-
Vegetation/Landscaping: Some cities require the addition of necessary landscape trees, not fruit trees. So, during the design period, you must discuss with the City what kind of trees to plant and where. You can request a list of approved species from the City and listen to their suggestions.
-
Survey: This is the foundation of all construction and often requires a third party to assess the property boundaries.
-
PG&E: Upgrading the electrical panel is the longest process; apply as early as possible.
A good designer usually handles these for you; if you have to do everything, something might be abnormal. But just to be safe, here are some key areas that are regulated.
Dealing with the City and Key Points for Plan Improvement (Integrated Version)
-
Initial Fact-Finding Before Project Initiation
-
Check the City's Zoning, Setback, Height, Lot Coverage, Parking requirements, and historical approval precedents.
-
Review neighborhood cases and street views to assess "prevalence of two stories," "style requirements," and "parking red lines."
-
Conduct a Pre-Application or Counter Meeting with a Planner early on to get verbal consensus and meeting minutes.
-
"Appro-vability" Optimization During the Design Phase
-
Concentrate the addition volume in directions that do not cross the red lines; use "internal rearrangement" instead of "external expansion" when necessary.
-
Height and Elevation: Use contour lines and sections to prove that the impact on neighbor's daylight and views is controllable.
-
Parking and Circulation: Clearly define parking space dimensions, turning radius, and circulation diagrams that avoid backing out onto an alley/street.
-
Trees and Landscaping: Mark the locations of trees to be preserved, transplanted trees, and newly added non-fruit trees, and attach a species list.
-
Consultants and Code Compliance
-
Fire Safety (Sprinkler/Smoke/CO): Pre-assess whether whole-house or partial upgrades and water meter size are triggered.
-
Energy Consumption and Envelope (Title 24): List window U-Factor, SHGC, and insulation levels item by item in the elevation table.
-
Structural and Exterior Wall Retention Ratio: Clarify the valuation and trigger line for "renovation vs. new construction."
-
Utilities: PG&E load calculation, conduit routing, meter relocation/modification; provide the shortest path and encroachment plan.
-
Submission Package and Review Mechanism
-
Submission Package Checklist: Site plan (with setbacks), all floor plans, elevations/sections, door/window schedule, detail drawings, structural notes, Title 24, tree and drainage plan, fire safety notes.
-
Naming and Versioning: Drawing number + version number, standardized annotation cross-referencing, mark "frozen points" and "change points."
-
Annotation Log/Tracking: Each comment → Responsible person → Solution → Does it require a second review → Estimated impact (Cost/Duration).
-
Neighborhood and Process Risk
-
Communicate with potentially affected neighbors in advance and record feedback; prepare shadow analysis maps and privacy countermeasures if necessary.
-
Pay attention to the Hearing and Notice periods, and prepare A/B options to reduce back-and-forth.
-
Permit and On-Site Coordination
-
Construction Hours and Noise: Arrange work sequencing according to municipal regulations, and lock in weekend restrictions in the contract beforehand.
-
Inspection Rhythm: Reverse schedule inspection points like Foundation, Framing, MEP Rough, Insulation, Drywall, etc.
-
Documentation: Formalize inspection results and verbal changes into written records within 24 hours for archiving.
0 comments